Day 34
- We planned for our Feb 21st Presentation
- We CADed the shooter wheel plates
- We made the Hex for our turret
- We made the mount for our motor that drives the turret
- We worked on the gear box for our collectors
- We finished the front of our safety flier
- We attached all of the belts and collectors
- We mounted the elevator and the motor to operate the elevator
- We worked on the Deans List Award
Main Achievement: WE SUBMITTED CHAIRMANS!
Day 34
Day 32
Day 32
- We went to Tucson High to borrow their bender and bent all of our pieces for our shooter! Thank you Tucson High!
- We started turning down the turret drive wheel
- We worked on the bumpers and bought the rest of the material for them.
- We had a pool noodle fight and one of our mentors even joined in :D
- We cut out the E-board (Emma board) and it fits on our robot
Main Achievement: Our tower is completely welded
Day 30
- We bought Duct Tape, brackets, fabric for bumpers, and grippy tape
- Made slots for our ball collector
- Programmers put tape on the backboards and tested it
- We finished our newsletter and sent it out
- Kelly from Purple Plasma, team 2403, came and collaborated with us
- Nick and Daniel from the NERDS, team 1726, came and collaborated as well:)
- We worked on fixing our lathe
- We worked on the bumpers
Main Achievement: We figured out how we are going to attach the ball elevator to the robot and made the necessary alterations to make it work.
Day 29
- We finished our gear box for the turret
- We worked on the bumpers
- We CADed the lexan ball director
- We planned a lot of the Dell Presentation
- We made the turret spin!
- We worked on improving our driver station
Main Achievement: WE FINISHED THE CHAIRMAN’S ESSAY AND EXECUTIVE SUMMARY
Day 28
Day 26